Road Construction (Class 1, 2 and 3)

Source: PEI Ecosystem-Based Forest Management Standards Manual (October 2025), Appendix 1, pp. 50–52

What it is

All three road classes are multipurpose woodlot access roads, with a crowned driving surface and modest ditches. They differ by the equipment they carry and the ground they cross:

Class Purpose Typical equipment
Class 1 Industrial-standard road for extracting forest products with large equipment Skidders, porters, trucks
Class 2 Low-impact road for extracting forest products with small equipment Tractors, ATVs
Class 3 Road through wet terrain, built up to carry more weight As required

Schematic cross-section of a crowned forest road showing right-of-way, travel surface, crown, shoulders and ditches

Dimensions by class

Class 1 Class 2 Class 3
Right-of-way (minimum) 8 m 5 m 8 m
Travel surface 4 m 3.5 m 4 m
Crown above shoulders 10–15 cm 10–15 cm where needed —
Shoulders above ditch base 15–30 cm, unless the plan says otherwise — —

Where there are no bullpens, the right-of-way must be at least 10 m wide.

Clearing the right-of-way

Building the road

Travel surface. All classes need a travel surface at least 300 mm deep when built with select borrow. Select borrow is specified in the Department of Transportation and Infrastructure’s General Provisions and Contract Specifications for Highway Construction, on the Government of PEI website.

Protecting adjacent trees. Bulldoze the right-of-way with as little damage as possible to the trees beside it; those trees must stay standing.

Surplus material:

Grades. No steeper than 10%, except over short distances. Even then, never more than 12%.

Ditches. Size and align them to carry runoff from moderate to severe storms, on every forest road.

Extra requirements for Class 3 (wet ground)

Materials for increasing bearing capacity:

Everything except slash is placed and shaped on the roadbed.

Element Standard
Geotextile cover At least 50 cm of shale and/or nearby soil
Slash mat cover At least 30 cm of shale and/or nearby soil
Source of on-site cover Dug from road ditches on both sides of the roadbed
Width between ditches No more than 6 m, except at turnarounds that are needed
Ditch side slopes No steeper than 2:1 on the shoulder side and 1.5:1 on the backslope
Drainage Ditches graded and aligned to drain properly
Junctions If ditched, turnarounds and branch roads need a culvert where they meet the road
Access points Entry and exit points roughly every 500 m of road, with culverts where appropriate

On ditch slopes. The manual states the ratios as “vertical to horizontal”, while its road diagram labels the slope as 1.5 horizontal to 1 vertical. Confirm the intended reading with your road designer.

Based on the PEI Ecosystem-Based Forest Management Standards Manual (October 2025), Appendix 1, pp. 50–52. Where this guide and the manual differ, the manual governs.